XP-82 Twin Mustang – September 2015 – Restoration Update

A color shot of the XP-82 back during its test flying days. (photo via Tom Reilly)
Aircorps Art Dec 2019

SSP SCHOLARSHIP LATEST UPDATE_GOOD ...
SSP SCHOLARSHIP LATEST UPDATE_GOOD NEWS_MANGEMENT STUDENTS_students solution

A color shot of the XP-82 back during its test flying days. (photo via Tom Reilly)
A color shot of the XP-82 back during its test flying days. (photo via Tom Reilly)

WarbirdsNews has received the latest XP-82 Twin Mustang restoration update from Tom Reilly at his workshop in Douglas, Georgia. Here’s what they’ve been up to this month!

Wings/Ailerons/Flaps

The final skinning and completion of the lower part of both outboard wings is now complete. The sheet metal team is doing the final fitting and riveting of the last outboard wing bulkhead. This outboard bulkhead holds the structural 10-32 nut plates that the wing tip attaches to. The drop-down pitot mast (airspeed indicator) has been test-fitted and completed. It is now at the cad plate shop and expected back any day now.

The sewing of the fabric gap-seal canvas is being completed. These fabric gap-seals create a barrier so that the airflow over and under the wings will not be able to transition through the gap between the aileron and the trailing edge of each wing.

Randall and Aymen  working on the wing... note how one of the men is actually inside the wing bucking the rivets. (photo via Tom Reilly)
Randall and Aymen working on the wing… note how one of the men is actually inside the wing bucking the rivets. (photo via Tom Reilly)
Finishing up the riveting on the final outboard wing bulkhead. The wing tip attaches at this station. (photo via Tom Reilly)
Finishing up the riveting on the final outboard wing bulkhead. The wing tip attaches at this station. (photo via Tom Reilly)
The completed outer wing panel. (photo via Tom Reilly)
The completed outer wing panel. (photo via Tom Reilly)

Fuel Tanks/Fuel Systems

Now that the wing skinning is complete, the four outboard tanks can now be permanently installed. The fuel capacity is 205 gallons total for each outboard wing, and there is a 95 gallon tank in each side of the center section, giving a total fuel capacity of 600 U.S. gallons. All of the fuel feed and fuel vent lines, along with the cross-feed check valves are now permanently installed along with the electrical conduits and internal wiring that run through or near the fuel tank bays, i.e. boost pumps (four) and liquidometers (six).

Electrical

The electrical team has been hooking up all of the electrical connections in both cockpits. They are about two-weeks away from completion, and at that time, Reilly’s team can put power on the ship and final-check each system. When the electrical system is final-checked and accepted, then the restoration team will install the completed instrument panels with their OHC (Overhauled Condition) instruments.

Left Hand pilot’s side electrical shelf partially completed with the temporary tie wraps prior to lacing cord. (photo via Tom Reilly)
Left Hand pilot’s side electrical shelf partially completed with the temporary tie wraps prior to lacing cord. (photo via Tom Reilly)

The fuel control box, which controls everything to do with fuel, i.e. boost pumps, fuel gauges, fuel shut-offs/cross-feed valves and drop tank(s), is now electrically bench-checked, completed and ready to be installed. This will be happen once the final testing of all the other circuits has been successfully proven.

The rear face of the fuel control box. (photo by Tom Reilly)
The rear face of the fuel control box. (photo by Tom Reilly)
The front face of the fuel control box, showing the two unique fuel gauges. (photo via Tom Reilly)
The front face of the fuel control box, showing the two unique fuel gauges. (photo via Tom Reilly)

Engines

The left-hand engine is now permanently installed, with the right-hand engine being installed next week, and all of the overhauled accessories will be installed in their respective positions on each engine, i.e. generators, governors, tach generators, fuel and vacuum pumps. Both overhauled engines came from Vintage V12s with the overhauled carburetors mounted.

The left hand Merlin engine is now mounted to the airframe. (photo via Tom Reilly)
The left hand Merlin engine is now mounted to the airframe. (photo via Tom Reilly)
Another view of the left hand engine in its mounts. (photo via Tom Reilly)
Another view of the left hand engine in its mounts. (photo via Tom Reilly)

Engine Cowlings

The sheet metal crew has started duplicating the ribs for a pair of right-hand upper and lower engine cowlings.

Some of the ribs coming together for the lower and upper engine cowlings. (photo via Tom Reilly)
Some of the ribs coming together for the upper and lower engine cowlings. (photo via Tom Reilly)
Newly machined radiator coolant neck identical to the original cast one. (photo via Tom Reilly)
Newly machined radiator coolant neck identical to the original cast one. (photo via Tom Reilly)
Newly machined aft up-lock latch hooks and trunnions for the main landing gear doors. (photo via Tom Reilly)
Newly machined aft up-lock latch hooks and trunnions for the main landing gear doors. (photo via Tom Reilly)

Many thanks again to Tom Reilly for the update! You can learn more about the project on their blog HERE. Please be sure to check back with WarbirdsNews in October for the next installment in the story following the XP-82′s road to recovery!